HYUNDAI Rotem confirmed on February 2 that it has been awarded a contract to supply rolling stock for the Jakarta LRT project.

The order for 16 two-car 1067mm-gauge trains is worth $US 33m and the total value of the order could reach $US 200m if options for up to 94 additional trains are exercised.

The Rupiah 11.9 trillion first phase of the elevated LRT network comprises Section 1 of Line 1 from Cibubur to Cawang (14.5km), Section 2 of Line 1 from Cawang to Dukuh Atas (10.5km) and the initial section of Line 2 from East Bekasi to Cawang (17.5km).

An 5.8km five-station section of Line 1 is due to open in time for the 2018 Asian Games, which will be held in Jakarta in August 2018.

The second phase of the network will add extensions at both ends of Line 1 together with a third line from Palmerah to Tomang and Grogol.